Thursday, April 2, 2009
Footings are set and poured
Roger and crew, Nate, Jamie and Joe set and poured the 200 + linear foot footing yesterday with no issues. Harrison Concrete brought in their big pump truck to make the reach 100+ feet. We plan on laying out and starting to set ICFs once the footing is stripped. The weather should work out for us over the next few days and if everything works out and the students are ready to push we should be setting staging early tommorrow and pouring early next week.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment